Particulars | No. of Working days receipt of application | |
|
Urban Areas | Rural Areas |
Extension of distribution mains not required | Within 7 working days | Within 10 working days |
Extension of distribution mains/ system required | ||
1. In case of LT service | Within 7 working days | Within 10 working days |
2. In case of HT service connections | Within 15 working days | Within 20 working days |
3. In case of EHT service | Within 30 working days | Within 30 working days |
Activity | Island areas | Mainland areas | ||
New connection/ additional load where supply can be provided from existing network | Urban area: 30 days from receipt of complete application | Urban area: 16 days from receipt of complete application | ||
Rural area: 30 days from receipt of complete application | Rural area: 24 days from receipt of complete application | |||
Extension work of enhancement of transformer capacity is required | Urban area: | Rural area: | Urban area: | Rural area: |
a) LT- 60 Days | a) LT-90 days | a) LT-30 days | a) LT-45 days | |
b) HT-120 days | b) HT-120 day | b) HT-90 day | b) HT-90 day | |
c) EHT-180 day | c) EHT-180 day | c) EHT-180 days | c) EHT-180 day | |
Erection of substation to extend Supply | On case to case basis as per approval of the Commission | On case to case basis as per approval of the Commission |
Activity | Island areas | Mainland areas |
Where supply can be provided from existing network | Urban area: 6 days | Urban area: 3 days |
Rural area: 14 days | Rural area: 7 days | |
Where supply can be provided after extension/ augmentation of network | Urban and Rural areas | Urban and Rural rears: |
a) LT-610 days | a) LT-30 days | |
b) HT-90 days | b) HT-90 days | |
c) EHT-180 days | c) EHT-180 days |
Urban Areas | Rural Areas | |
Conversion from LT single phase to LT 3 phase or vice- versa | Within two billing cycles from payment of necessary charges by consumer | Within tow billing cycles from payment of necessary charges by Consumer |
Conversion from LT to HT or vice- versa | Within two billing cycles from payment of necessary charges by consumer | Within two billing cycles from payment of necessary charges by consumer |
Conversion from HT to EHT or vice versa | Within four billing cycles from payment of necessary charges by consumer | Within four billing cycles from payment of necessary charges by consumer |
S. No. | Item | Time Limit (within) |
1 | Aggregate Loads up to 100 kVA | 10 days of receipt of Application |
2 | Aggregate Loads above 100 kVA and up to 400 kVA | 15 days of receipt of Application |
3 | Aggregate Loads above 4000 kVA | 30 days of receipt of Application |