Completion of Various Activities

Circular

Data has been taken from Supply code 2018


Timeline for issue of Demand Note:
Particulars No. of Working days receipt of application

 

Urban Areas Rural Areas
Extension of distribution mains not required Within 7 working days Within 10 working days
Extension of distribution mains/ system required
1. In case of LT service Within 7 working days Within 10 working days
2. In case of HT service connections Within 15 working days Within 20 working days
3. In case of EHT service Within 30 working days Within 30 working days
Timeline for releasing new electricity connection (energization):
Activity Island areas Mainland areas
New connection/ additional load where supply can be provided from existing network Urban area: 30 days from receipt of complete application Urban area: 16 days from receipt of complete application
Rural area: 30 days from receipt of complete application Rural area: 24 days from receipt of complete application
Extension work of enhancement of transformer capacity is required Urban area: Rural area: Urban area: Rural area:
a) LT- 60 Days a) LT-90 days a) LT-30 days a) LT-45 days
b) HT-120 days b) HT-120 day b) HT-90 day b) HT-90 day
c) EHT-180 day c) EHT-180 day c) EHT-180 days c) EHT-180 day
Erection of substation to extend Supply On case to case basis as per approval of the Commission On case to case basis as per approval of the Commission
Timeline for release of temporary connection:
Activity Island areas Mainland areas
Where supply can be provided from existing network Urban area: 6 days Urban area: 3 days
Rural area: 14 days Rural area: 7 days
Where supply can be provided after extension/ augmentation of network Urban and Rural areas Urban and Rural rears:
a) LT-610 days a) LT-30 days
b) HT-90 days b) HT-90 days
c) EHT-180 days c) EHT-180 days
Timeline for Conversion of services:
  Urban Areas Rural Areas
Conversion from LT single phase to LT 3 phase or vice- versa Within two billing cycles from payment of necessary charges by consumer Within tow billing cycles from payment of necessary charges by Consumer
Conversion from LT to HT or vice- versa Within two billing cycles from payment of necessary charges by consumer Within two billing cycles from payment of necessary charges by consumer
Conversion from HT to EHT or vice versa Within four billing cycles from payment of necessary charges by consumer Within four billing cycles from payment of necessary charges by consumer
Timeline for raising Demand Note for Additional Load
S. No. Item Time Limit (within)
1 Aggregate Loads up to 100 kVA 10 days of receipt of Application
2 Aggregate Loads above 100 kVA and up to 400 kVA 15 days of receipt of Application
3 Aggregate Loads above 4000 kVA 30 days of receipt of Application